"Conditions of Contract for Plant and Design-Build" in accordance with international regulations and national legislation.
Works contract 3202/06.05.2011 was signed between SC ECOAQUA SA and SC SIREG SA, leader of the consortium SC SIREG SA and SC TMUCB & SC TELPRON COMEX SRL & SC DUNAREA PROIECT GRUP SA.
The updated value of the contract: 21.472.622,71 lei excluding VAT.
Contract Duration: 32 months until 30.01.2014, with Defects Notification Period of min 12/max 24 months- contract completed on the 21.07.2016.
The project comprises new water supply and treatment plants for Budesti, Oltenita, Fundulea and Lehliu-Gara agglomerations incl. design, obtaining approvals, rehabilitation and new works including wellfields, storage reservoirs, treatment plants and pumping stations, raw water mains, treated water mains and SCADA systems for each agglomeration, operator training, testing and commissioning.